Running Petitions






Sr No Petition No/year Petitioners Respondents Subject Section Last Hearing Date Attachments
1 45/2021

[Licensing & Regulation ]

1) M/s ReNew Power Private Limited, Delhi
1) Managing Director, MP Power Management Company Limited
In the matter of petition under section 86 of the Electricity Act 2003 for (i) quashing of Letter dated 18.01.2021 issued by the Respondent disallowing Petitioner’s claim for ‘Change in Law’ (ii) Approval of “Change in Law” and (iii) Seeking an appropriate mechanism for grant of an appropriate djustment/compensation to offset financial/ commercial impact of change in law events on account of imposition of safeguard duty on solar cells/modules in terms of Article 11 read along with Article 13.3 of the Power Purchase Agreements dated 10.11.2015 between the petitioner and Respondent. Section 86 of the Electricity Act, 2003 30-07-2025 View Daily Orders