Sr No | Petition No/year | Petitioners | Respondents | Subject | Section | Date of Order | Attachments |
---|---|---|---|---|---|---|---|
1 | 1/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition under section 06 (1)(1) of the Electricity Act, 2003, for adjudication of the dispute between the Petitioner and Respondent relating to incentive payable as per regulation 36.4 of the Madhya Pradesh Electricity Regulations Commission (Terms and conditions for determination of Generation Tariff) Regulations, 2015 and Regulation 42.6 of the Madhya Pradesh Electricity Regulations Commission (Terms and Conditions for determination of Generation Tariff) Regulations, 2020. | Section 86 of the Electricity Act, 2003 | 23-Apr-2024 |
|
2 | 2/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Petition seeking extension of relaxation granted under Petition No. 17 of 2022 in line with the Clause 8.1 read with Clause 11.19 & Clause 11.22 of the Madhya Pradesh Electricity Supply Code 2021 from Mandatory installation of smart pre-payment meter for all new connections as well as for replacement of the stopped/defective/burnt meters and to extend such relaxation for electrification of PVGT/other households. | - | 05-Mar-2024 |
MPERC Gazette Notification No 622 dated 06/03/2024 Notified on 08/03/2024 |
|
3 | 3/2024 |
1) BLA Power Pvt. Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition under Section 86(1)(f) of the Electricity Act, 2003 for recovery of dues payable by MPPMCL to the Petitioner under the terms of the Power Purchase Agreement dt. 05.01.2011 for the months of April\' 2020 and May\' 2020. | Section 86 of the Electricity Act, 2003 | 21-Feb-2024 |
|
4 | 4/2024 |
1) M.P. Urja Vikas Nigam Limited |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition for determination of pre-fixed levelized tariff for sale of power from decentralized Solar Power Plants having capacity of five hundred kW to two MW or such other capacity as per notification of Govt. of India, to be set up under Component-A of the PM KUSUM Scheme introduced by Government of India | - | 27-Feb-2024 |
|
5 | 5/2024 |
1) MP Poorva Kshetra Vidyut Vitran Company Limited |
Petition for revised CAPEX Application (Capital Investment Plan) for the period FY 2022-23 to FY 2026-27 for obtaining approval of the Commission for various schemes as per Regulation 10.3 of the MPERC (The Conditions of Distribution License for Distribution Licensees (including Deemed Licensees), Regulations 2004 by MPPOKVVCL, Jabalpur as the Distribution Licensee. | - | 27-Feb-2024 |
|
|
6 | 6/2024 |
1) Surendra Kumar Verma |
1) Union of India, Ministry of Power 2) M.P. State Electricity Board, 3) General Manager, MPMKVVCL, Bhopal 4) Assistant Engineer , MPMKVVCL, Betul 5) State of MP, through Collector, Betul |
Petition for old flat/ fix rate earlier on the farmer agriculture electricity use. | - | 28-May-2024 |
|
7 | 7/2024 |
1) M P Power Transmission Company Limited |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) M.P. Industrial Development Corporation Ltd. (MPIDC) 5) West Central Railways, Jabalpur |
Review Petition seeking review/modification of the Order dt. 12.12.2023 passed by the Commission in Petition No. 55/2023. | Section 94 of Electricity Act, 2003 | 22-Apr-2024 |
|
8 | 8/2024 |
1) M P Power Transmission Company Limited |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited 5) M.P. Industrial Development Corporation Ltd. (MPIDC) 6) West Central Railways, Jabalpur |
Application for approval of Capital Investment plan for Transmission works to coincide with the control period of MYT (2024-25 to 2028-29) | - | 03-Sep-2024 |
Annexure-I Previously Approved Works |
9 | 9/2024 |
1) Managing Director, MP Power Management Company Limited |
1) Jindal India Thermal Power Ltd. (JITPL) 2) Jindal Power Ltd. (JPL) 3) SKS Power Generation Chhattisgarh Ltd. (SKS) 4) RKM Powergen Pvt. Ltd. (RKM) 5) TRN Energy Pvt. Ltd. (TRN) 6) PFC Consulting Ltd. |
Merged Petition for approval of Power Purchase Agreement to be signed by MPPMCL for procurement of power from thermal generating stations selected through competitive bidding process conducted by PFC Consulting Ltd. under guidelines of Ministry of Power. | Section 86 of the Electricity Act, 2003 | 05-Apr-2024 |
|
10 | 10/2024 |
1) M P Power Transmission Company Limited |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) M.P. Industrial Development Corporation Ltd. (MPIDC) 5) West Central Railways, Jabalpur |
Filing an application regarding provisional tariff for FY 2024-25 and FY 2025-26 | - | 15-Mar-2024 |
|
11 | 11/2024 |
1) K. N. Agri Resources Limited (Earlier known as Itarasi Oils and Flours Pvt. Ltd.) |
1) Managing Director, MP Power Management Company Limited 2) MP Pashchim Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) M P Power Transmission Company Limited |
Petition under Section 86(1)(e) & (f) of the Electricity Act, 2003 for restitution of PPWA dated 23.02.2012 and for suitable compensation of damages | Section 86 of the Electricity Act, 2003 | 20-Jun-2024 |
|
12 | 12/2024 |
1) SUO MOTO PETITON by MPERC |
1) M.P. Industrial Development Corporation Ltd. (MPIDC) |
Notice under section 142 of the Electricity Act 2003 read with the provisions of regulation 15 of the MPERC (Cogeneration and Generation of Electricity from Renewable Sources of Energy), Regulations 2010 & 2021 for failure to comply with the RPO targets during the period FY 2010-11 to 2021-22 | Section 142 of the Electricity Act 2003 | 29-Apr-2024 |
|
13 | 13/2024 |
1) M.P. Urja Vikas Nigam Limited |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Revised Petition for determination of pre-fixed levelized tariff for sale of power from decentralized Solar Power Plants having capacity of five hundred kW to two MW or such other capacity as per notification of Govt. of India, to be set up under Component-A of the PM KUSUM Scheme introduced by Government of India and revised petition for the same. | - | 20-Jun-2024 |
|
14 | 14/2024 |
1) SUO MOTO PETITON by MPERC |
In the matter of approval for provisional billing by MPPTCL from 01/04/2024 till issue of MYT Order for new control period starting from 01/04/2024 | Sections 61 of the Electricity Act 2003 | 05-Mar-2024 |
|
|
15 | 15/2024 |
1) SUO MOTO PETITON by MPERC |
In the matter of approval for provisional billing by Generating Companies from 01.04.2024 till issuance of MYT orders for respective Generating Companies for new control period starting from 01.04.2024 | Sections 61 of the Electricity Act 2003 | 05-Mar-2024 |
|
|
16 | 16/2024 |
1) Porwal Auto Components Pvt Ltd(Solar Division) |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited |
In the matter off seeking Partial Clarification on the Commission’s order dated 22/09/2023 in Petition no. 17/2023, Petition Under Section 86(1)(e) of the Madhya Pradesh Electricity Act, 2003. | Section 86 of the Electricity Act, 2003 | 19-Mar-2024 |
|
17 | 17/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
1) M.P. Urja Vikas Nigam Limited 2) Principal Secretary, MP New and Renewable Energy Department, Govt. of M.P |
Petition under Clause 16&17 of MPERC (Grid Interactive Renewable Energy System and Related Matters) Regulation, 2022 seeking appropriate regulatory dispensation & guidance from the Commission to address the issues identified with certain provision of existing Regulations related to Energy Accounting and Settlement and accordingly requesting the Commission either to amend the existing provision or allow Net Billing or Gross Metering as an alternate solution. | - | 23-Aug-2024 |
|
18 | 18/2024 |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition, Under Section 94 (1) (f) of the Electricity Act, 2003 read with Regulation 40 of the MPERC (Conduct of Business) (Revision-1) Regulations 2016 and invoking all other powers available in this behalf, seeking review and/or recall and/or modification of the Order dated 02.02.2024 in the SMP No. 37/2023 | Section 86 of the Electricity Act, 2003 | 13-Aug-2024 |
|
|
19 | 19/2024 |
1) M/s. VE Commercial Vehicles Ltd., |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited 2) Managing Director, MP Power Management Company Limited 3) M/s Bhadresh Trading Corporation Limited , Mumbai |
Petition seeking appropriate directions and orders to set aside demand notice dated 27.12.2018 of MPPKVVCL and further directions to them to refund the amount deposited under protest by the petitioner towards the said demand notice. | Section 86 of the Electricity Act, 2003,Section 82 of the Electricity Act, 2003 | 13-Aug-2024 |
|
20 | 20/2024 |
1) MP Poorva Kshetra Vidyut Vitran Company Limited |
Petition for revised CAPEX Application (Capital Investment Plan) for the period FY-2022-23 to FY 2026-27 for obtaining approval of the Commission for various schemes as per Regulation 10.3 of the MPERC (The Conditions of Distribution License for Distribution Licensees (including Deemed Licensees), Regulations 2004 by MPPKVVCL, Jabalpur as the Distribution Licensee. | - | 04-Sep-2024 |
|
|
21 | 21/2024 |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition for DSM plan under \"Capacity Building of Discom\" program on demand side management and energy efficiency during 2017-21. | - | 30-Apr-2024 |
|
|
22 | 22/2024 |
1) Smt Preeti Choube W/o Rajendra Sharma |
1) Executive Engineer, MP Madhya Kshetra Vidyut Vitarn Co. Ltd Vidisha (MP) |
Petition under Section 142 and 146 of the Electricity Act 2003 | Section 142 of the Electricity Act 2003,Section 146 of the Electricity Act, 2003 | 20-Sep-2024 |
|
23 | 23/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Review Petition under section 94 (1) (F) of the electricity act, 2003 read with order 47 rule 1 of the code of civil procedure, 1908 and regulation 40 of the Madhya Pradesh Electricity Regulatory Commission (Conduct of Business) (Revision-1) Regulations, 2016 for review of order dt. 28.02.2024 passed in Petition No. 62 of 2023. | Section 94 of Electricity Act, 2003,Regulation 40 of the Madhya Pradesh Electricity Regulatory Commission (Conduct of Business) | 13-Aug-2024 |
|
24 | 24/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited |
Review Petition under section 94(1) (F) of the electricity act, 2003 read with regulations 6(6) and 40 of the Madhya Pradesh Electricity Regulatory Commission (Code of Conduct) (Revision-1) Regulations, 2016 and order 47 rule 1 of the Code of Civil procedure, 1908 seeking review of the order dt. 22.02.2024 passed by this Hon\\\'ble Commission in Petition No. 63 of 2023. | Section 94 of Electricity Act, 2003,Regulation 40 of the Madhya Pradesh Electricity Regulatory Commission (Conduct of Business) | 13-Aug-2024 |
|
25 | 25/2024 |
1) M.P. Industrial Development Corporation Ltd. (MPIDC) |
1) Managing Director, MP Power Management Company Limited 2) M P Power Transmission Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) Govt. of Madhya Pradesh, Energy Department |
Petition for Amendment in Area of Distribution License (DL/1 dated 16th June, 2021) for notified Industrial Area Mohasa-Babai, Narmadapuram, M.P. Under Section 18 of the Electricity Act, 2003. | Section 18 of the Electricity Act, 2003 | 12-Nov-2024 |
|
26 | 26/2024 |
1) M P Power Generating Company Limited |
1) Managing Director, MP Power Management Company Limited 2) M P Power Transmission Company Limited 3) Rajasthan Rajya Vidyut Prasaran Nigam Ltd., Jaipur 4) Uttar Pradesh Power Corporation Ltd., Lucknow 5) MSEB (Holding Co) & Maharashtra State Transmission Co. Ltd, Mumbai |
Review Petition/ application under section 94(1)(f) of the Electricity Act, 2003 read with MPERC (Conduct of Business) Regulations, 2016 seeking corrigendum on account of error apparent on the face of record in order dated 07.03.2024 in Petition No. 71 of 2023 towards Trueup of Generation tariff of MPPGCL\'s Thermal and Hydro Power Stations for FY 2022-23 determined by MPERC vide Multi Tear Tariff order dated 19.05.2021 in Petition No. 53 of 2020 read with corrigendum dated 09.09.2021 | Section 94 of Electricity Act, 2003 | 23-Aug-2024 |
|
27 | 27, 28 and 29/2024 |
1) M/s. LANXESS India Pvt. Ltd. , THANE, MH 2) Campus Polyplast Pvt. Ltd. 3) M/s Mukesh Associates, Indore |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited 2) Managing Director, MP Power Management Company Limited |
Petitions under Section 9, 42 and 86 of the Electricity Act, 2003 read with Rule 3 of the Electricity Rules, 2005 and Sections 142, 146 and 149 of the Electricity Act, 2003, challenging levy of additional surcharge on captive power. | Section 142 of the Electricity Act 2003,Section 86 of the Electricity Act, 2003,Section 42 of the Electricity Act, 2003,Section 9 of the Electricity Act, 2003,Section 146 of the Electricity Act, 2003,Section 149 of the Electricity Act, 2003 | 07-Oct-2024 |
|
28 | 30/2024 |
1) NKS Complex , Indore (MP) |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition filed under section 46 of the Act and clause 6.5, 6.6 of MPERC (Recovery of Expenses and other charges for providing electric line or plant used for the purpose of giving supply) (Revision-II Regulation 22 RG-31 (II) of 2022 dated 31st May 2022. | - | 24-Sep-2024 |
|
29 | 31/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition Seeking Necessary Regulatory Dispensation through Practice Directions under the Clause 11.23 Read with Clause 11.19 of the Madhya Pradesh Electricity Supply Code 2021 for Executing an Agreement with the Consumers and allowing the Consumer to Self-Certify/Upload the Contractor\\\'s Test Report through Online Mode. | - | 12-Jun-2024 |
|
|
30 | 32/2024 |
1) MB Power (Madhya Pradesh) Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition under section 86 of the Electricity Act, 2003 read with MPERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020 and its amendments notified thereafter seeking Supplementary Tariff in respect of implementation of Flue-Gas Desulphurization System in the coal based Anuppur Thermal Power Project of MB Power (Madhya Pradesh) Limited in District Anuppur of Madhya Pradesh in compliance of the Revised Emission Standards prescribed by MoEF&CC\'s Notification dated 07.12.2015. | Section 86 of the Electricity Act, 2003 | 31-Dec-2024 |
|
31 | 33/2024 |
1) Jindal Power Ltd. (JPL) |
1) Managing Director, MP Power Management Company Limited |
Petition under section 94 (1) (f) of the Electricity Act, 2003 and Order 47 Rule 1 of the CPC, 1908 seeking review of the order dated 05.04.2024 passed by the Hon\'ble Commission in Petition No. 09 of 2024 | Section 94 of Electricity Act, 2003 | 13-Aug-2024 |
|
32 | 34/2024 |
1) M/s ACME Solar Energy (MP) Pvt. Ltd., Gurugram, Haryana |
1) Managing Director, MP Power Management Company Limited |
Petition under section 86 of the Electricity Act 2003 before the MPERC seeking (i) Approval for installation of the additional modules to repower and enhance the DC capacity of the Petitioners Solar Power Project without increasing the AC capacity or contracted capacity to meet energy obligations mentioned in the Power Purchase Agreement dated 01.08.2012 executed between the Petitioner and the Respondent. | Section 86 of the Electricity Act, 2003 | 12-Mar-2025 |
|
33 | 35/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Review Petition Under Section 94(1)(F) of the electricity act, 2003 read with order 47 rule 1 of the code of civil procedure, 1908 and regulation 40 of the MPERC (Conduct of Business) (Revision-1) Regulations, 2016 for review of order dt. 23.04.2024 passed in Petition no. 1 of 2024. | Section 94 of Electricity Act, 2003 | 23-Aug-2024 |
|
34 | 36/2024 |
1) SUO MOTO PETITON by MPERC |
1) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Notice under section 142 of the Electricity Act, 2003 | Section 142 of the Electricity Act 2003 | 26-Sep-2024 |
|
35 | 37/2024 |
1) SUO MOTO PETITON by MPERC |
1) The Chief Electrical Distribution Engineer, West Central Railway, Jabalpur |
Notice under section 142 of the Electricity Act 2003 for non-compliance of RPO Obligation as per provisions of MPERC (Cogeneration and Generation of Electricity from Renewable Sources of Energy) Regulations, 2021 (Revision-II) as amended and directions of the Commission from time to time during the period 2020-21 to 2023-24. | Section 142 of the Electricity Act 2003 | 19-Sep-2024 |
|
36 | 38/2024 |
1) SUO MOTO PETITON by MPERC |
1) Managing Director, MP Power Management Company Limited |
Notice under section 142 of the Electricity Act 2003 for non-compliance of RPO Obligation as per provisions of MPERC (Cogeneration and Generation of Electricity from Renewable Sources of Energy) Regulations, 2021 (Revision-II) as amended and directions of the Commission from time to time during the period 2020-21 to 2023-24. | Section 142 of the Electricity Act 2003 | 18-Dec-2024 |
|
37 | 39/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition seeking extension and modification in relaxation granted under Petition No. 02 of 2024 in line with the Clause 8.1 read with Clause 11.19 & Clause 11.22 of the Madhya Pradesh Electricity Supply Code 2021 from mandatory installation of smart pre-payment meter or pre-payment meter for all new connections and for replacement of the existing meters (including stopped/defective/burnt meters) with Smart Pre-payment meters and to extend such relaxation for electrification of PVGT/other households. | - | 23-Aug-2024 |
MP Gazette Notification dated 30-08-2024 |
|
38 | 40/2024 |
1) Patanjali Foods Limited (Formerly : Ruchi Soya Industries Limited), Indore |
1) Chief General Manager (Commercial NCE), MP Power Management Company Limited 2) Superintending Engineer (O&M) , MP Pashchim Kshetra Vidyut Vitran Company Limited, Dewas, MP 3) Managing Director, MP Power Management Company Limited |
Petition under section 86 (1)(e) & (f) of the Electricity Act, 2003 (as amended upto date), read with section 9 (a)(0) and 9(r) of the MP Vidyut Sudhar Adhiniyam, 2000, for passing an appropriate order with respect to the management and administration of the affairs of the licensee respondent, in the matter of grant of permission for extension of period of PPWA dt. 18.01.2012 for machine at N-2, which is going to expire on 17.10.2024 and another PPWA of even dt. 18.01.2012 for machine at N-5 location expiring on 24.01.2025. | Section 86 of the Electricity Act, 2003 | 13-Aug-2024 |
|
39 | 41/2024 |
1) M.P. Power Transmission Package - I Limited |
1) Managing Director, MP Power Management Company Limited 2) REC Power Development and Consultancy Limited 3) Govt. of Madhya Pradesh, Energy Department 4) M P Power Transmission Company Limited |
Petition Under Section 86(1)(C), 86(1) (F) and 86(1)(K) of the Electricity Act, 2003 along with regulation 45 of the MPERC (Conduct of Business) Regulations, 2016 read with article 4.4, article 11, article 16 and other relevant clauses of the transmission service agreement dated 21.01.2023 executed between the petitioner and the long-term transmission customers for seeking extension of scheduled commercial operation date on account of force majeure events and consequential reliefs arising therefrom. | Section 86 of the Electricity Act, 2003 | 01-Oct-2024 |
|
40 | 42/2024 |
1) Managing Director, MP Power Management Company Limited |
Petition seeking amendments, addition and clarification on certain provision of MPERC (Methodology for determination of Open Access charges and Banking charges for Green Energy Open Access consumers) Regulations 2023. | Section 181 of Electricity Act 2003 | 05-Nov-2024 |
|
|
41 | 43/2024 |
1) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Petition seeking necessary practice direction concerning sub-clause (i) of clause 4.84 of the Madhya Pradesh Electricity Supply Code 2021 and its subsequent amendments. | - | 12-Aug-2024 |
|
|
42 | 44/2024 |
1) M/s SAP Energy,C/o Shrenik Marble (P) Ltd. |
1) Managing Director, MP Power Management Company Limited |
Petition Under Section 142 of the Electricity Act, 2003 for disobedience and contempt proceedings for non-compliance of order dated 28.11.2022 and 21.09.2023 of the Hon\'ble Commission. | Section 142 of the Electricity Act 2003 | 06-Nov-2024 |
|
43 | 46/2024 |
1) K. N. Agri Resources Limited (Earlier known as Itarasi Oils and Flours Pvt. Ltd.) |
1) Managing Director, MP Power Management Company Limited 2) MP Pashchim Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) M P Power Transmission Company Limited |
Petition Under section 94 (1) (f) of the Electricity act, 2003 seeking review of the impugned order dated 20-06-2024 passed in petition no. 11/2024 | Section 94 of Electricity Act, 2003 | 07-Oct-2024 |
|
44 | 47/2024 |
1) M P Power Generating Company Limited |
1) Managing Director, MP Power Management Company Limited |
Petition to avail Special Allowance for Unit #4 (210MW) of PH-2, SGTPS, Birsinghpur under proviso 28 of MPERC Regulations, 2024 (RG-26(V) of 2024). | - | 08-Nov-2024 |
|
45 | 48/2024 |
1) M/s Grasim Industries (Chemical Division) Birla Gram, Dist. UJJAIN (M.P.). |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited 2) M.P. Urja Vikas Nigam Limited |
Request for approval to purchase/ adjust RECs and procure backlogs/ carry forward RPO from open market from 19.11.2010 to FY 2023-2024. | Section 86 of the Electricity Act, 2003 | 23-Sep-2024 |
|
46 | 49/2024 |
1) M/s Grasim Industries Ltd. Steple Fiber Division, Nagda |
1) MP Pashchim Kshetra Vidyut Vitran Company Limited 2) M.P. Urja Vikas Nigam Limited |
Request for approval to purchase RECs and procure backlogs RPO from open market from 19.11.2010 to FY 2023-2024 for Compliance of RPO Obligations. | Section 86 of the Electricity Act, 2003 | 19-Sep-2024 |
|
47 | 50/2024 |
1) M/s Soumya Homes Pvt. Ltd., Bhopal |
1) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Section 142 of the Electricity Act, read with Section 28 of MP Vidyut Sudhar Adhiniyam, 2000; & In the matter of contravention of the provisions of the Electricity Act, 2003 and the regulations made thereunder by the Respondent; & In the matter of contravention of the order of Ld. Electricity Consumer Grievance Redressal Forum by the Respondent. | Section 142 of the Electricity Act 2003 | 31-Dec-2024 |
|
48 | 51/2024 |
1) BLA Power Pvt. Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Consolidated petition for Multi Year Tariff (FY 2024-25 to FY 2028-29) for sale of Contracted Capacity of MP Power Management Company Ltd., from the entire Generating Station of M/s B LA Power Pvt. Ltd., comprising of 2 Units of 45 MW each (i.e. Unit-1 & Unit-2) | - | 13-Feb-2025 |
|
49 | 52/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Multi Year Tariff petition under Section 62 and Section 86(1)(a) of the Electricity Act, 2003, read with the MPERC (Terms and Conditions for determination of Generation Tariff) Regulations, 2024 (RG-26(V) of 2024} for determination of Generation Tariff under the Multi Year Tariff framework for the 2 x 250 MW Coal based Thermal Power Station at Bina, District Sagar, Madhya Pradesh, for the Control Period from FY 2024-25 to 2028-29. | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 28-Feb-2025 |
|
50 | 53/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Multi Year Tariff petition under Section 62 and Section 86(1)(a) of the Electricity Act, 2003, read with the MPERC (Terms and Conditions for determination of Generation Tariff) Regulations, 2024 (RG-26(V) of 2024) for determination of Generation Tariff under the Multi Year Tariff framework for the 2 x 660 MW Super Critical Coal based Thermal Power Station at Nigrie, District Singrauli, Madhya Pradesh, for the Control Period from FY 2024-25 to 2028-29. | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 28-Feb-2025 |
|
51 | 54/2024 |
1) M P Power Transmission Company Limited |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) M.P. Industrial Development Corporation Ltd. (MPIDC) 5) West Central Railways, Jabalpur |
Filing of application for determination of the Transmission Tariff for control period FY 2024-25 to FY 2028-29. | - | 20-Mar-2025 |
|
52 | 55/2024 |
1) Korba Power Limited (formerly known as Lanco Amarkantak Power Limited) 2) M/s. PTC India Ltd. 3) Managing Director, MP Power Management Company Limited |
Petition under section 64(5) read with Section 62 and Section 86 (1) (a) & (b) of the Electricity Act, 2003 for determination of tariff for FY 2024-25 to FY 2028-29 in accordance with applicable MPERC (Terms & Conditions for Determination of Generation Tariff) Regulations, 2024 against long term power supply to MP Power Management Co. Ltd., (\'MPPMCL\') through PTC India Ltd., (\'PTC\') from the 300 MW Unit I of M/s. Korba Power Limited (\'KPL\') (formerly known as Lanco Amarkantak Power Ltd.), Pathadi, Korba, Chhattisgarh coal based thermal power plant. | Section 86 of the Electricity Act, 2003,Sections 64 of the Electricity Act 2003 | 14-Nov-2024 |
|
|
53 | 56/2024 |
1) M P Power Generating Company Limited |
1) Managing Director, MP Power Management Company Limited 2) M P Power Transmission Company Limited 3) Rajasthan Rajya Vidyut Prasaran Nigam Ltd., Jaipur 4) Uttar Pradesh Power Corporation Ltd., Lucknow 5) MSEB (Holding Co) & Maharashtra State Transmission Co. Ltd, Mumbai |
Petition for Determination of Multi Year Generating Tariff of Power Stations of MPPGCL for the Control Period FY 2024-25 to FY 2028-29 under Section 62 & 86(i) (a) of the Electricity Act 2003 based on MPERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2024. | Section 86 of the Electricity Act, 2003,Sections 64 of the Electricity Act 2003 | 04-Mar-2025 |
|
54 | 57/2024 |
1) MB Power (Madhya Pradesh) Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition under Section 62 and 86 (1)(a) of the Electricity Act, 2003 read with Part VII of the Electricity Act, 2003 for determination of Multi-year tariff for the coal based Anuppur Thermal Power Project of MB Power (Madhya Pradesh) at District Anuppur, Madhya Pradesh for the coal period from 01st April 2024 to 31st March 2029 under the MPERC (Terms and Conditions for determination of Genertion Tariff) Regulations, 2024 (RG-26 (V) of 2024). | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 28-Feb-2025 |
|
55 | 58/2024 |
1) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Filing of petition for necessary amendment in Clause 7.29 of Madhya Pradesh Electricity Supply Code 2021 seeking necessary regulatory dispensation through required amendments in MP Electricity Supply Code. | - | 12-Dec-2024 |
|
|
56 | 59/2024 |
1) Deepak Spinners Ltd., Solan, HP |
1) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Petition under section 86 (1) of the Electricity Act, 2003 read with clause 45, 46 and 47 of MPERC (Conduct of Business) (Revision-1) Regulations, 2016 for seeking appropriate directions for grant of rebate of incremental consumption and rebate for captive power plant consumers to the petitioner as per clause (D) and (F) as specified in specific terms and conditions of tariff schedule-HV-3 Industrial, non-industrial and shopping malls. | Section 86 of the Electricity Act, 2003 | 09-Dec-2024 |
|
57 | 60/2024 |
1) SUO MOTO PETITON by MPERC |
In the matter of simplified charges for new service connections in electrified areas under section 46, 86(1) and 181 of the Electricity Act, 2003 read with Regulations 6.5 and 6.6 of the MPERC (Recovery of Expenses and other Charges for Providing Electric Line or Plant used for the purpose of giving Supply) Regulations, 2022. | Section 86 of the Electricity Act, 2003,Regulation-46 of MPERC (Conduct of Business),Section 181 of Electricity Act 2003 | 11-Dec-2024 |
|
|
58 | 61/2024 |
1) M.P. Power Transmission Package - I Limited |
1) Managing Director, MP Power Management Company Limited 2) Catalyst Trusteeship Limited 3) REC Power Development and Consultancy Limited 4) M P Power Transmission Company Limited |
Petition filed under sections 17(3) & 17(4) of the Electricity Act, 2003 for seeking approval for creation of security interest over all of the petitioner\'s assets in favour of Respondent No. 2 (M/s Catalyst Trusteeship Limited) acting for the benefit of the Lender) (or any of their assignees, transferees or novates) in respect of the petitioner\'s project. | Section 17(3) of the Electricity Act, 2003,Section 17(4) of the Electricity Act, 2003 | 30-Dec-2024 |
|
59 | 63/2024 |
1) BLA Power Pvt. Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition for True-up of tariff for FY 2023-24 for sale of Contracted Capacity to MP Power Management Co. Ltd., from the Generating Station of B LA Power Pvt. Ltd., comprising of 2 Units of 45 MW each (i.e. Unit-1 & Unit-2). | Section 62 of the Electricity Act, 2003 | 21-Mar-2025 |
|
60 | 64/2024 |
1) MB Power (Madhya Pradesh) Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
Petition under section 62 and Section 86(1)(a) of the Electricity Act, 2003 read with Part VII of the Electricity Act, 2003 for True-up of Tariff for coal based Anuppur Thermal Power Project (Phase-I) comprising of Unit-1 & Unit-2 at District Anuppur, Madhya Pradesh for the period from 01st April 2023 to 31st March 2024 under MPERC (Terms and Conditions for determination of Generation Tariff) Regulations, 2020 (RG-26 (IV) of 2020). | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 28-Mar-2025 |
|
61 | 65/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
True-Up Petition under Section 62 and Section 86(1)(a) of the Electricity Act, 2003 read with the MPERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020 (RG-26 (IV) of 2020) for True-up of Tariff in respect of FY 2023-24 determined by the Hon\\\'ble Commission vide Multi Year Tariff Order dated 03-05-2021 of its Coal Based 2 x 660 MW Super Critical Thermal Power Station at Nigrie, District Singrauli, MP, due to additional capital expenditure incurred by the Petitioner during Financial Year 2023-24. | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 08-Apr-2025 |
|
62 | 66/2024 |
1) M/s Jaiprakash Power Venture Ltd |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Madhya Khsetra Vidyut Vitran Compnay Limited 4) MP Pashchim Kshetra Vidyut Vitran Company Limited |
True-Up Petition under Section 62 and Section 86(1)(a) of the Electricity Act, 2003 read with Regulation 9.4 of the MPERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2020 (RG-26 (IV) of 2020) for True-up of Tariff in respect of FY 2023-24 determined by the Hon\\\'ble Commission vide Multi Year Tariff Order dated 30-04-2021 of its 2 x 250 MW (Phase 1) Coal Based Power Project at Bina, Dist. Sagar, Madhya Pradesh, due to additional capital expenditure incurred by the Petitioner during Financial Year 2023-24. | Section 62 of the Electricity Act, 2003,Section 86 of the Electricity Act, 2003 | 01-Apr-2025 |
|
63 | 67/2024 |
1) SLDC State Load Dispatch Center |
Levy and Collection of fee and charges by State Load Despatch Centre (SLDC) Jabalpur for the Year 2025-26 | - | 04-Mar-2025 |
|
|
64 | 68/2024 |
1) M P Power Transmission Company Limited |
1) MP Poorva Kshetra Vidyut Vitran Company Limited 2) MP Madhya Khsetra Vidyut Vitran Compnay Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) M.P. Industrial Development Corporation Ltd. (MPIDC) 5) The Chief Electrical Distribution Engineer, West Central Railway, Jabalpur |
In the matter of filing of application of True-up of the Transmission Tariff for FY 2023-24. | - | 18-Mar-2025 |
|
65 | 69/2024 |
1) Korba Power Limited (formerly known as Lanco Amarkantak Power Limited) |
1) M/s. PTC India Ltd. 2) Managing Director, MP Power Management Company Limited |
Petition under section 64(5) read with Section 62 and Section 86(1)(a) & (b) of the Electricity Act, 2003 for true-up of tariff for FY 2023-24 and Petition for true-up of tariff for FY 2023-24 earlier determined by the Hon\\\'ble Commission order dated 13.05.2022 for M/s Lanco Amarkantak Power Ltd., Pathadi, Korba, Chhattisgarh, coal based thermal power plant 300 MW Unit 1 under Section 64(5) read with Section 62 and Section 86(1)(a) & (b) of the Electricity Act, 2003 as per MPERC (Terms & Conditions for determination of Generation Tariff) Regulations, 2020. | Section 86 of the Electricity Act, 2003,Sections 64 of the Electricity Act 2003 | 28-Mar-2025 |
|
66 | 70/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Petition for True up of ARR for FY-2023-24 | - | 28-Mar-2025 |
|
|
67 | 71/2024 |
1) M.P. Industrial Development Corporation Ltd. (MPIDC) |
Petition for True up of ARR for FY-2023-24 | - | 29-Mar-2025 |
|
|
68 | 72/2024 |
1) Managing Director, MP Power Management Company Limited 2) MP Poorva Kshetra Vidyut Vitran Company Limited 3) MP Pashchim Kshetra Vidyut Vitran Company Limited 4) MP Madhya Khsetra Vidyut Vitran Compnay Limited |
Petition for Revised ARR & Tariff proposal for FY-2025-26 | - | 29-Mar-2025 |
|
|
69 | 73/2024 |
1) M.P. Industrial Development Corporation Ltd. (MPIDC) |
Petition for ARR & Tariff proposal for FY-2025-26 | - | 08-Apr-2025 |
|
|
70 | 74/2024 |
1) M/s Nahar Spinning Mills Ltd |
1) M.P. Urja Vikas Nigam Limited |
Petition under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 40 of MPERC (Conduct of Business) Regulations, 2016 and Order 47 Rule 1 of the Code of Civil Procedure, 1908 for review of order dated 04.10.2024 passed in SUO MOTO Petition No. 45 of 2024. | Section 94 of Electricity Act, 2003 | 22-Jan-2025 |
|
71 | 75/2024 |
1) West Central Railways, Jabalpur |
1) M.P. Urja Vikas Nigam Limited |
Petition for review and modification of the Order dated 19.09.2024 passed by this Hon\\\'ble Commission in Suo Moto Petition No. 37 of 2024 under section 94(1)(1) of the Electricity Act, 2003 read with Regulations 40 and 45 of the MPERC (Conduct of Business) Regulations, 2016 read with Regulation 18 and Regulation 19 of MPERC (Co- generation and Generation of Electricity from Renewable Sources of Energy) Regulations, 2021. | Section 94 of Electricity Act, 2003,Regulation-45 of MPERC (Conduct of Business) | 28-Mar-2025 |
|
72 | 76/2024 |
1) M P Power Generating Company Limited |
1) Managing Director, MP Power Management Company Limited 2) M P Power Transmission Company Limited 3) Rajasthan Rajya Vidyut Prasaran Nigam Ltd., Jaipur 4) Uttar Pradesh Power Corporation Ltd., Lucknow 5) MSEB (Holding Co) & Maharashtra State Transmission Co. Ltd, Mumbai |
True-up of Generation Tariff of Power Stations of MPPGCL for FY 2023-24 determined by MPERC vide Multi Year Tariff order dated 19.05.2021 read with corrigendum dated 09.09.2021. | Sections 61 of the Electricity Act 2003,Section 181 of Electricity Act 2003 | 08-Apr-2025 |
|
73 | 79/2024 |
1) SUO MOTO PETITON by MPERC |
Suo moto petition in the matter of Determination of Tariff for Procurement of Power from Small Hydro Projects in M.P. | Sections 61 of the Electricity Act 2003 | 20-Feb-2025 |
|
Copyright © 2024 - MPERC.
Contents Provided, Updated & Maintained By
MPERC, Bhopal (M.P.)
Disclaimer : While every care has been taken to ensure the accuracy of information furnished in this website, MPERC does not accept any responsibility or liability for any damage or loss to any person for the result of any action taken on the basis of this information. However, MPERC shall be obliged if errors/omissions are brought to its notice for carrying out corrections in the next update.