Item No Petition No/Year Petitioner Respondents Detail Hearing Date Remark
1 26/2026

I.A. Number 12 of 2026

[Licensing & Regulation ]

1) Rewa Ultra Mega Solar Ltd., Bhopal

1) Managing Director, MP Power Management Company Limited

Petition under Guidelines 17 of the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Firm and Dispatchable Power from Grid Connected Renewable Energy Power Projects with Energy Storage Systems (Resolution No. 23/03/2023-R&R) issued by the Ministry of Power, Government of India on 09.06.2023 (as amended from time to time) under section 63 of the Electricity Act, 2003, seeking deviations from the aforementioned guidelines. 19-May-2026

12:00 PM

Motion Hearing
2 2/2026

[Licensing & Regulation ]

1) Apraava Renewable Energy Pvt. Ltd., Ahmedabad (Gujarat) (formerly CLP Wind Farms (India) Pvt. Ltd.,)

1) Managing Director, MP Power Management Company Limited

Petition under Sections 86(1) (b), (c), (e), (f), (i) and (k) of the Electricity Act, 2003 read with Regulations 9, 10 and 17 of the Madhya Pradesh Electricity Regulatory Commission (Conduct of Business) Regulations, 2016. 19-May-2026

12:00 PM

Hearing
3 12/2026

[Licensing & Regulation ]

1) M.P. Urja Vikas Nigam Limited

1) Managing Director, MP Power Management Company Limited

2) M P Power Transmission Company Limited

3) The Chief Engineer, SLDC

Petition under Para 1(b) of Appendix-K of Madhya Pradesh Grid Code, 2024, read with section 86(1)(e) of the Electricity Act, 2003, for determination of reactive power compensation for RE Generators injecting in the distribution grid at HT level. 19-May-2026

12:00 PM

Hearing
4 45/2025

[Licensing & Regulation ]

1) M/s. Ashuvibha Power Pvt Ltd

1) M.P. Urja Vikas Nigam Limited

2) Managing Director, MP Power Management Company Limited

Petition u/s. 86 (1) (b) (e) and (f) of the Electricity Act, 2003 seeking enhancement in tariff on account of Change-in-Law increase in Goods and Services Tax on Capital Items and Related Services w.e.f. 01-11-2021 in relation to its ground mounted Solar Power Plants of 2 MW capacity installed by the Petitioner under Component A of PM KUSUM Scheme at Village Kudaila, Tahsil Bichiya, District Mandla (M.P.). 19-May-2026

12:00 PM

Hearing
5 122/2025

[Licensing & Regulation ]

1) M/s Arya Energy Limited, Raipur

1) Managing Director, MP Power Management Company Limited

Petition under section 86(1)(B), Section 86(1)(E), Section 86(1) (F), Section 86(1)(K) and 86(4) of the Electricity Act, 2003 for adjudication of dispute with Madhya Pradesh Power Management Co. Ltd. 19-May-2026

12:00 PM

Hearing
6 123/2025

[Licensing & Regulation ]

1) M/s Continuum MP Windfarm Development Pvt. Ltd. Jaora, Ratlam, (MP)

1) Managing Director, MP Power Management Company Limited

2) Principal Secretary, MP New and Renewable Energy Department, Govt. of M.P

3) MP Madhya Khsetra Vidyut Vitran Compnay Limited

4) MP Pashchim Kshetra Vidyut Vitran Company Limited

5) MP Poorva Kshetra Vidyut Vitran Company Limited

Petition filed under section 86(1)(e), (f) & (k) and other applicable provisions of the Electricity Act, 2003 read with Regulation 45 of Madhya Pradesh Electricity Regulatory Commission (Conduct of Business) (Revision-1) Regulations, 2016 (RG-10(1) of 2016) for issuing directions to the respondents to provide the incentives granted to the Petitioner's 200MW Wind Solar Hybrid Project under Madhya Pradesh Renewable Energy Policy, 2022 19-May-2026

12:00 PM

Hearing
7 1/2026

[Licensing & Regulation ]

1) M/s. LANXESS India Pvt. Ltd. , THANE, MH

1) The Chief Engineer, SLDC

2) MP Pashchim Kshetra Vidyut Vitran Company Limited

Petition under Regulation 10 of the MPERC (Verification of Captive Generating Plants and Captive Users) Regulations, 2023 (as amended), read with Regulations 47 and 48 of MPERC (Conduct of Business) (Revision-1) Regulations, 2016 and Sections 9 and 42 of the Electricity Act, 2003, seeking clarifications/ directions qua the Revised Detailed Procedure for Verification of Status of Captive Generating Plants and Captive Users issued vide Orders dated 03.07.2024 and 27.05.2025, on the applicability and format of FORM-11 [under clause 3.1.2(a) (iv)] in cases where the captive generating plant is established, owned and operated directly by the captive user and does not involve a separate special purpose vehicle. 19-May-2026

12:00 PM

Arguments
8 10/2026

I.A. Number 05 and 06 of 2026

[Tariff]

1) M.P. Power Transmission Package - I Limited

1) Managing Director, MP Power Management Company Limited

2) REC Power Development and Consultancy Limited

3) Energy Dept. GoMP

4) M P Power Transmission Company Limited

Petition under Sections 86(1)(C), 86(1)(F) and 86(1)(K) of the Electricity Act, 2003, along with Regulation 45 of the Madhya Pradesh Electricity Regulatory Commission. (Conduct of Business) Regulations, 2016 read with Article 4.4, Article 11, Article 16 and other relevant clauses of the Transmission Service Agreement dated 21.01.2023 executed between the Petitioner and the Long-Term Transmission customers for seeking extension of scheduled commercial operation date on account of force majeure events and consequential reliefs arising therefrom. 19-May-2026

12:00 PM

Arguments
9

Public Hearing in the matter of draft 2nd Amendment to Madhya Pradesh Electricity Regulatory Commission (Verification of captive generating plants and Captive Users), Regulations, 2023 (G-45 of 2026). 19-May-2026

12:00 PM

Public Hearing
Cause List of 26-May-2026
Item No Petition No/Year Petitioner Respondents Detail Hearing Date Remark
1 18/2026

[Licensing & Regulation ]

1) M/s. Jaideep Ispat & Alloys (P)Ltd.

1) MP Pashchim Kshetra Vidyut Vitran Company Limited

Petition under Sections 9 and 86(1)(f) of the Electricity Act, 2003 read with rule 3 of the Electricity Rules, 2005 26-May-2026

12:00 PM

Motion Hearing
2 19/2026

[Licensing & Regulation ]

1) UltraTech Cement Limited

1) MP Poorva Kshetra Vidyut Vitran Company Limited

2) The Chief Engineer, SLDC

Petition under sections 86(1)(f) of the Electricity Act, 2003 read with Regulations 6.4 and 10 of the MPERC (Verification of Captive Generating Plants and Captive Users) Regulations, 2023. 26-May-2026

12:00 PM

Motion Hearing
3 22/2026

[Tariff]

1) M.P. Power Transmission Package-II Limited (Adani Transmission Limited)

1) Union Bank of India

2) Catalyst Trusteeship Limited

3) Managing Director, MP Power Management Company Limited

4) M P Power Transmission Company Limited

Petition under Sections 17(3) & 17(4) of Electricity Act, 2003 seeking approval for creation of security interest over all of the Petitioner's Assets in favour of Respondent No. 2- the Security Trustee acting for the benefit of the Lender in respect of the Petitioner's transmission project. 26-May-2026

12:00 PM

Motion Hearing
4 23/2026

[Regulatory Enforcement ]

1) Association of All Industries

1) MP Madhya Khsetra Vidyut Vitran Compnay Limited

Petition under Clause 3.1 & 3.2 of the Madhya Pradesh Electricity Regulatory Commission (Power Quality) Regulations, 2025. 26-May-2026

12:00 PM

Motion Hearing
5 24/2026

[Licensing & Regulation ]

1) M/s Rathi Iron & Steel Industries ,Indore

1) Managing Director, MP Power Management Company Limited

2) MP Pashchim Kshetra Vidyut Vitran Company Limited

3) M P Power Transmission Company Limited

Petition under Section 86(1)(k) of the Electricity Act, 2003 Read with Clauses 7.33, 7.34, 11.18, 11.19, 11.22 and 11.23 of the MP Electricity Supply Code 2021 and Regulation 45 & 48 of MPERC (Conduct of Business) (Revision-1) Regulations, 2016, Seeking Appropriate Directions and Order to Respondents. 26-May-2026

12:00 PM

Motion Hearing
6 7/2026

I.A. Number 1 of 2026

[Licensing & Regulation ]

1) M/s Continuum MP Windfarm Development Pvt. Ltd. Jaora, Ratlam, (MP)

1) Principal Secretary, MP New and Renewable Energy Department, Govt. of M.P

2) M P Power Transmission Company Limited

3) Managing Director, MP Power Management Company Limited

4) SLDC State Load Dispatch Center

Petition under section 86 of the Electricity Act, 2003 read with Regulation 20 and 22 of the MPERC (Terms and Conditions for Intra-State Open Access in Madhya Pradesh) Regulations, 2021 and the relevant provisions of the Madhya Pradesh Renewable Energy Policy 2025, seeking clarification on the development of a non-co-located Wind-Solar Hybrid Project. 26-May-2026

12:00 PM

Hearing
7 147/2025

[Licensing & Regulation ]

1) PM Mitra Park Madhya Pradesh Limited

1) MP Pashchim Kshetra Vidyut Vitran Company Limited

2) M P Power Transmission Company Limited

3) Managing Director, MP Power Management Company Limited

4) Energy Dept. GoMP

In the matter of application for grant of power distribution license under Section 14 and Section 15 of the Electricity Act, 2003 and as per the MPERC {Procedure, Terms and conditions for Grant of Distribution License and other matters of Distribution Licensee (including Deemed Licensee)} Regulations, 2025 (Revision-1) (RG-12(1) of 2025. 26-May-2026

12:00 PM

Hearing
8 45/2021

[Licensing & Regulation ]

1) M/s ReNew Power Private Limited, Delhi

1) Managing Director, MP Power Management Company Limited

In the matter of petition under section 86 of the Electricity Act 2003 for (i) quashing of Letter dated 18.01.2021 issued by the Respondent disallowing Petitioner’s claim for ‘Change in Law’ (ii) Approval of “Change in Law” and (iii) Seeking an appropriate mechanism for grant of an appropriate djustment/compensation to offset financial/ commercial impact of change in law events on account of imposition of safeguard duty on solar cells/modules in terms of Article 11 read along with Article 13.3 of the Power Purchase Agreements dated 10.11.2015 between the petitioner and Respondent. 26-May-2026

12:00 PM

Hearing
9 146/2025

I.A. Number 32 of 2025 & IA No 8 of 2026

[Tariff]

1) SLDC State Load Dispatch Center

2) M P Power Transmission Company Limited

1) M/s Continuum MP Windfarm Development Pvt. Ltd. Jaora, Ratlam, (MP)

Petition under Section 94(1)(f) of the Electricity Act, 2003 for review of order dated 17.11.2025 passed in Petition No. 19/2025 read with Clause 40, 45 and 46 MPERC (Conduct of Business) Regulations, 2016. 26-May-2026

12:00 PM

Arguments
10 6/2026

[Tariff]

1) Korba Power Limited (formerly known as Lanco Amarkantak Power Limited)

2) M/s. PTC India Ltd.

1) Managing Director, MP Power Management Company Limited

Public Hearing in the matter of Petition no 06 of 2026 filed by Korba Power Limited and PTC India Ltd. for determination of Multi-Year Tariff from FY 2024-25 to FY 2028-29 of its 300 MW Unit No. 1 coal based Thermal Power Project at Pathari village, Distt. Korba, Chhattisgarh. 26-May-2026

12:00 PM

Public Hearing
11

Public hearing in the matter of draft first amendment to Madhya Pradesh Electricity Grid Code, 2024 26-May-2026

12:00 PM

Public Hearing